Alba Potline 4 Aluminium Plant, Bahrain

 
Synopsis:
Civil and structural design
Contractor:
Klöckner Industrie-Anlagen
End Client:
ALBA

Tony Gee provided the complete civil and structural design and detailing for a new 13,500 sq. m Anode Rodding Shop, a 45 m high Bath Treatment Tower including silos, and analysis and modifications for existing Anode Rodding Shop.

Together with the upgrade of the Raw Material Handling systems, including modifications to the Marine Loading facility, this project doubled the capacity of the smelting plant.

Our scope also included airlift towers and pits, 5,000 tonne and 12,500 tonne silo supports, airslide bridges, conveyor bridges, access towers, marine store, loading silos, storage building with loading hoppers, substations, furnace building, PLC and MCC rooms.

Quick Links
Alba Potline 4 Aluminium Plant

Print this page Print this page
 

Leave a Reply

Sectors

Nullam tristique ornare est non interdum. Phasellus eget augue felis, et congue dui. Aenean hendrerit consectetur placerat. Nulla elementum tellus sed metus posuere.

 

Careers

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Duis congue orci sit amet neque pulvinar ultricies. Maecenas ac mauris id libero ultricies porta.

Nullam tristique ornare est non interdum. Phasellus eget augue felis, et congue dui. Aenean hendrerit consectetur placerat. Nulla elementum tellus sed metus dapibus posuere. Maecenas nec diam sed neque imperdiet tortor. Aenean hendrerit consectetur placerat.

Apply now

Services

  • Research and development
  • Inspections and assessments
  • Feasibility studies
  • Ground investigations
  • Permanent works design
  • Temporary works design
  • Lifting and moving systems
  • Design checking
  • Demolition and façade retention
  • Construction methodology
  • Site monitoring
  • Expert witness

Brochure