Alba Potline 4 Aluminium Plant, Bahrain

Synopsis:
Civil and structural design
Contractor:
Klöckner Industrie-Anlagen
End Client:
ALBA

Tony Gee provided the complete civil and structural design and detailing for a new 13,500 sq. m Anode Rodding Shop, a 45 m high Bath Treatment Tower including silos, and analysis and modifications for existing Anode Rodding Shop.

Together with the upgrade of the Raw Material Handling systems, including modifications to the Marine Loading facility, this project doubled the capacity of the smelting plant.

Our scope also included airlift towers and pits, 5,000 tonne and 12,500 tonne silo supports, airslide bridges, conveyor bridges, access towers, marine store, loading silos, storage building with loading hoppers, substations, furnace building, PLC and MCC rooms.

Quick Links
Alba Potline 4 Aluminium Plant